Legislative Decree — Conciliation and Arbitration - Article 27
Congreso Nacional
- Published: September 29, 2026
- Issuing body: Congreso Nacional
- Gazette: 37,258
- Category: Administrative
Summary
This law restructures the state-owned electricity company (ENEE) by splitting it into three separate generation, transmission, and distribution companies, all under state control. The goal is to improve operational efficiency, modernize electrical infrastructure, and allow each company to operate independently, while protecting the country's strategic assets.
Articles
ARTICLE 27: CONCILIATION AND ARBITRATION. The parties may resort to the Conciliation and Arbitration Center of the Chamber of Commerce and Industry of Tegucigalpa to resolve their disputes or controversies, without prejudice to their ability to agree upon the seat, applicable rules, and other conditions under which they may, if applicable, be subject to a conciliation or arbitration procedure. Should such conditions not be agreed upon, the provisions of the Conciliation and Arbitration Law shall apply. The award issued in the arbitration procedure shall be final.
ARTICLE 3: TRANSFORMATION OF THE NATIONAL ELECTRIC POWER COMPANY (ENEE). A. TRANSFORMATION AND SEPARATION OF ENEE INTO SUBSIDIARY COMPANIES. The transformation and division of the National Electric Power Company (ENEE) is hereby ordered, adopting the form of single-person anonymous commercial companies whose sole shareholder is the State of Honduras, in accordance with the provisions of Article 4 of the General Law of the Electrical Industry for the authorization of enterprises in the electrical subsector. To that effect, the National Electric Power Company (ENEE) shall be transformed and divided into one or more generation, distribution, and transmission companies, which shall be owned by the State through the National Electric Power Company (ENEE) as the parent company. For purposes of this Decree, division is understood to mean the corporate reorganization by which the National Electric Power Company (ENEE) separates legally, operationally, administratively, financially and accounting-wise the activities of generation, transmission, and distribution, maintaining the National Electric Power Company (ENEE) Parent the ownership of goods and assets that the State transfers to it and assigning them to the subsidiary companies solely for their administration, operation, maintenance, and custody, through the execution of Administration Contracts, without transfer of ownership. The current Board of Directors of the National Electric Power Company (ENEE) described in Legislative Decree No. 48, dated February 27, 1957, and its amendments, containing the "CONSTITUTIVE LAW OF THE NATIONAL ELECTRIC POWER COMPANY," is hereby constituted as the new Board of Directors of the National Electric Power Company (ENEE) Parent. To that end, the Board of Directors of the National Electric Power Company (ENEE) is instructed to determine the infrastructure assets corresponding to each business unit of generation, transmission, and electrical energy distribution activities, which shall remain under the ownership of the National Electric Power Company (ENEE) Parent and shall be assigned to the subsidiary companies through Administration Contracts for their administration, operation, maintenance, and custody, without transfer of ownership; as well as to determine the liabilities, personnel, accounts receivable, other credit rights and contracts corresponding to each business unit and to order their transfer to the subsidiary companies created, with absolute respect for the labor rights of workers. Likewise, the Board of Directors of the National Electric Power Company (ENEE) is authorized to execute and fully pay the initial capital stock of each subsidiary company, in accordance with the provisions of section B.b) of this article, as well as to perform, by itself or through the officials it designates, all acts necessary for the division ordered herein, being administratively responsible in case of non-compliance. Similarly, the Board of Directors of the National Electric Power Company (ENEE) shall determine the assets, technological resources, and personnel assigned to the functions of control center and dispatch operations used by the system operator, and order their transfer or delivery in loan to the System and Market Operator, respecting the rights of workers affected. The full effectiveness of the division ordered by this Decree shall occur upon the registration of the minutes of the division agreement and constitution of the subsidiary companies issued by the Board of Directors in the Commercial Registry of Francisco Morazán. The Commercial Registry of Francisco Morazán shall create as many registry entries as necessary for each of the subsidiary companies resulting from the transformation and division process, with the division agreement serving as the constitutive act of each commercial company. The right of users of electrical service to install, operate, and use their own electrical energy generation systems with renewable resources, such as photovoltaic solar systems or other clean technologies, to fully or partially cover their consumption, is recognized, and they may remain connected to the grid or request disconnection in accordance with applicable technical, safety, and quality standards. The surplus of renewable energy that such users inject into the grid shall be compensated in accordance with the tariff, methodology, or compensation mechanism established by the Electrical Energy Regulatory Commission (CREE). B. COMMON CHARACTERISTICS OF SUBSIDIARY COMPANIES. The subsidiary companies resulting from the transformation and division process shall have the following characteristics: a) Nature and designation. They shall be constituted as single-person anonymous commercial companies, with administrative, technical, operational, and financial autonomy, under the designations of: • National Electric Power Company Generation, Single-Person Anonymous Company; • National Electric Power Company Transmission, Single-Person Anonymous Company; and, • National Electric Power Company Distribution, Single-Person Anonymous Company, which may be divided or create subsidiaries by regions in the country. b) Capital stock. The initial capital stock of each company shall be ONE HUNDRED FIFTY MILLION LEMPIRAS (L.150,000,000.00), fully subscribed and paid by the National Electric Power Company (ENEE) Parent, in its capacity as sole shareholder. The number, class, and nominal value of the shares shall be determined in the respective constitutive act; c) State ownership and sole shareholder. The State of Honduras shall be the exclusive owner of the capital stock of the subsidiary companies, through the National Electric Power Company (ENEE), in its capacity as parent company, which shall be the sole shareholder and holder of one hundred percent (100%) of the shares representing the capital stock of each company. No shareholders other than the National Electric Power Company (ENEE) Parent may be incorporated nor shall shares be issued or allocated to third parties; d) Domicile. The social domicile shall be the City of Tegucigalpa, Municipality of the Central District, without prejudice to each company being able to establish offices, agencies, branches, or subsidiaries in any location of the Republic of Honduras; e) Purpose. The National Electric Power Company Generation, Single-Person Anonymous Company, shall have as its purpose the generation of electrical energy and the administration, operation, maintenance, rehabilitation, modernization, and expansion of the generation plants and assets owned by the National Electric Power Company (ENEE) Parent that are assigned to it for the fulfillment of its purpose, without transfer of ownership; The National Electric Power Company Transmission, Single-Person Anonymous Company, shall have as its purpose the transmission of electrical energy and the administration, operation, maintenance, modernization, and expansion of the national transmission network and its associated assets, owned by the National Electric Power Company (ENEE) Parent, that are assigned to it for the fulfillment of its purpose, without transfer of ownership. The National Electric Power Company Distribution, Single-Person Anonymous Company, shall have as its purpose the regulated distribution and commercialization of electrical energy, including measurement, billing, collection, customer service, operation, maintenance, modernization, and expansion of the distribution networks owned by ENEE Parent that are assigned to it for administration and operation, without transfer of ownership. f) Form of administration. Each subsidiary company shall be administered by a Board of Directors. Its composition, requirements, powers, terms, incompatibilities, accountability regime, and functioning shall be established in the respective bylaws. Members shall be appointed by the National Electric Power Company (ENEE) Parent, in its capacity as sole shareholder, and shall demonstrate technical, financial, administrative, or legal experience related to the electrical subsector and shall be subject to conflict of interest rules. They may not represent the interests of potential buyers, private generators, contractors, suppliers, or other private agents that maintain or intend to maintain business relations with the corresponding company. C. EXEMPTION. The National Electric Power Company (ENEE) and the companies established for purposes of the modernization and corporate division ordered in this Decree are hereby exempt from the payment of registration fees, taxes, duties, and levies applicable to their constitution and capitalization, and to the transfer or cession of assets, liabilities, contracts, and personnel, as well as to the instruments that must be executed as a direct or indirect consequence of the modernization process of the National Electric Power Company (ENEE). D. AUTHORIZATION FOR TRANSFER OF ASSETS TO ENEE. The Executive Power, through the Secretariat of State for Finance (SEFIN), shall transfer to the National Electric Power Company (ENEE) the infrastructure assets of generation, transmission, and distribution of electrical energy owned by the State currently operated by the National Electric Power Company (ENEE), including the structural work of hydroelectric dams and the installations that make up the national transmission network, distribution network, and substations operated by the National Electric Power Company (ENEE), as well as the rights of way, easements, and land associated with these installations, and any other property of the State operated or in the possession of the National Electric Power Company (ENEE), which shall be inventoried by the Board of Directors of the National Electric Power Company (ENEE) and which shall remain under the ownership and assets of the National Electric Power Company (ENEE) Parent and shall be assigned to the corresponding subsidiary companies through the execution of Administration Agreements, according to their function, solely for their administration, operation, maintenance, and custody, without transfer of ownership. Works, improvements, expansions, replacements, and investments that the subsidiary companies make with respect to such assets shall be incorporated into the assets of the National Electric Power Company (ENEE) Parent. All assets and properties that the State transfers to the National Electric Power Company (ENEE) Parent, the shares of the subsidiary companies, and the strategic assets that these acquire after the entry into force of this Decree are non-transferable and non-alienable and may not be used as collateral for financing. Capital flows or cash flows generated by the subsidiary companies may be used as collateral to support financing required for the operation, expansion, or growth of said companies. The assignment of assets and properties of the National Electric Power Company (ENEE) Parent to the subsidiary companies shall not constitute a transfer of ownership nor a capital contribution, nor shall it confer real rights upon the subsidiaries over said assets. ENEE Parent shall retain its ownership and custody of the State's patrimonial interest. ENEE Parent may not sell, cede, transfer, donate, pledge, encumber, or transfer, in whole or in part, the shares that compose the capital of the subsidiary companies without authorization from the National Congress. Neither may shares, convertible obligations, or other instruments be issued that reduce or dilute the participation of ENEE Parent below one hundred percent (100%). E. RIGHTS OF SUBSIDIARIES OVER ASSIGNED ASSETS. Without transferring the ownership of the assets, which belongs exclusively to the National Electric Power Company (ENEE) Parent, each subsidiary shall have the exclusive right to use, operate, maintain, improve, and expand the assets assigned to it for the provision of its services, as well as to receive and manage the economic benefits derived from their use and exploitation. This right shall be enforceable against the National Electric Power Company (ENEE) Parent and shall be exercised in accordance with the powers and attributions established by law of the Electrical Energy Regulatory Commission (CREE) and of the System and Market Operator (OSM). The rights, obligations, and specific conditions for the exercise of these rights shall be developed in the respective Administration Agreements executed by the National Electric Power Company (ENEE) Parent and each subsidiary. Such agreements must guarantee, among other things, the following aspects:
- a)
Duration and validity of the right of use and administration of the assets, including its term and renewal conditions, which shall not be less than thirty (30) years;
- b)
Irrevocability and protection of the assigned assets;
- c)
Autonomy of management of the subsidiary with respect to the operation, maintenance, improvement, and investment in the assets, without prejudice to the rights of the National Electric Power Company (ENEE) Parent as owner and shareholder;
- d)
Ownership and management of income, indemnifications, and other economic benefits derived from the activity of the subsidiary;
- e)
Powers of contracting, insurance, collection of indemnifications, use of compatible uses, and legal defense of the assets, as well as the management of easements, expropriations, and registrations necessary; and, f) The identification of the assets, term, exclusive use, income, maintenance, investments, insurance, responsibilities, compensations, and accounting treatment in accordance with International Financial Reporting Standards (IFRS) that may be applicable. F. PROTECTION OF ENEE ASSETS. The properties, reservoirs, protective strips, installations, and areas of influence of the hydroelectric plants owned by the National Electric Power Company (ENEE) are hereby declared public domain assets, non-seizable, non-transferable, and non-alienable, of national security and social interest. Any occupation, invasion, human settlement, cultivation, or unauthorized use of the properties, reservoirs, protective strips, installations, and areas of influence of the hydroelectric plants owned by the National Electric Power Company (ENEE) Parent, including those assigned to its subsidiaries for administration and operation, declared as public domain assets in accordance with this section, is hereby prohibited and shall constitute a crime when applicable. The National Electric Power Company (ENEE), in coordination with the Special Environmental Prosecution Office, the National Police, the Armed Forces, and the competent judicial authorities, shall proceed to the immediate eviction and restoration of the invaded properties. The National Electric Power Company (ENEE) shall maintain an updated cadastre of its real property assets and shall report annually to the Electrical Energy Regulatory Commission (CREE). Within the framework of the division described in this Decree, a specific budget shall be allocated for surveillance, signage, fencing, and reforestation of the riparian protection strips, in accordance with forestry legislation and applicable environmental standards. ENEE Generation shall have within its structure a unit for patrimonial and environmental protection, with technical personnel responsible for the surveillance of the properties and the execution of a comprehensive management plan for the areas delimited in and around the reservoirs. ENEE Generation may execute coordination agreements with associations of municipalities in areas of influence, municipal governments, the Secretariat of State for Risk and National Contingency Management (COPECO), and the Institute of Forest Conservation (ICF), Secretariat of State for Natural Resources and Environment (SERNA), for integrated basin management and emergency response. G. TRANSITIONAL REGIME FOR INCOME TAX EXEMPTION. In order to guarantee the economic and financial feasibility, operational sustainability, and economic independence of the companies resulting from the division process of the National Electric Power Company (ENEE), a transitional regime of exemption from the Income Tax (ISR) is hereby established for a period of ten (10) years, counted from the effective start of operations of each of the companies resulting from the division. During said period, the beneficiary companies shall be exempt from payment of the Income Tax (ISR) corresponding to net income, profits, or gains derived directly from the development of the activities proper to the electrical subsector for which they were established, including generation, transmission, distribution, commercialization, and other activities that legally correspond to them. The exemption established in this article shall have as its purpose to allow the companies resulting from the division to retain and reinvest the resources generated by their operations, strengthening their capitalization, liquidity, investment capacity, maintenance, and expansion of electrical infrastructure, as well as their capacity to operate efficiently and with financial independence. The exemption established in this article is exclusive to the National Electric Power Company (ENEE) and the companies that result directly from its division process and shall not be extended, in any case, to contractors, subcontractors, suppliers, consultants, concessionaires, private operators, affiliated companies, business partners, or any other natural or legal person that maintains contractual, commercial, or any other nature of relationships with the National Electric Power Company (ENEE) or with the companies resulting from the division. H. INITIAL CONTRACT. The electrical energy distribution and generation subsidiary companies resulting from the restructuring process of the National Electric Power Company (ENEE) are hereby authorized to execute an initial contract or contracts for coverage of energy and capacity from the generation plants owned by the National Electric Power Company (ENEE) Parent assigned for administration and operation to the generation subsidiary company, for a maximum term of ten (10) years. The price of such contracts shall be determined by the Electrical Energy Regulatory Commission (CREE) based on technical studies of efficient costs that consider, at a minimum, the efficient costs of operation and maintenance, the investments necessary to ensure availability, security, and continuity of supply, and a reasonable return on recognized capital. Initial contracts must be approved by the Electrical Energy Regulatory Commission (CREE), shall be subject to the general rules of the national electrical wholesale market, and their costs shall be integrated into the generation costs recognized in the tariff of end users, in the terms established by applicable regulation. In order to ensure the sustainability of public generation, distribution companies are hereby ordered to execute initial ten (10)-year contracts with ENEE Generation in the terms approved by the Electrical Energy Regulatory Commission (CREE), without such contracts entailing alterations to the economic dispatch that negatively affect the tariff to the end user. I. INVESTMENTS AND IMPROVEMENTS. The subsidiary's investments shall be recorded in accordance with IFRS standards. If a work or improvement becomes the property of the National Electric Power Company (ENEE) Parent, this shall simultaneously recognize an account receivable or a capital contribution for the same value and in favor of the subsidiary.
ARTICLE 4: ROLE OF ENEE AS PARENT COMPANY. Upon completion of the division ordered in this Decree, the National Electric Power Company (ENEE), in representation of the State of Honduras, shall be in charge of exercising ownership of one hundred percent (100%) of the shares representing the capital stock of the subsidiary companies and administering the resources derived from such ownership, retaining ownership, custody of the patrimonial interest that the State transfers to it, and assigning them to the subsidiary companies for their administration, operation, maintenance, and custody, without transfer of ownership, assuming as its sole role that of parent company of the subsidiary companies created or to be created as a result of its transformation, and custodian of the patrimonial interest of the State, with the other functions assigned to it by the Regulation and General Government Policy approved by the Board of Directors within this role. The aforementioned Regulation must guarantee the operational, technical, and administrative autonomy of the subsidiary companies in the exercise of their activities, without prejudice to the powers of the ENEE parent to exercise its corporate rights and establish general guidelines of corporate governance, in accordance with this Decree. The National Electric Power Company (ENEE) shall ensure and demand efficient professional administration of the subsidiary companies, oriented toward the development of services in the medium and long term, guaranteeing that they operate with complete autonomy in the pursuit of defined objectives, and refraining from intervening in ordinary management. The National Electric Power Company (ENEE) shall permit the subsidiary companies to act with independence and prioritize the loyalty of their respective boards of directors to the interest of the company they administer and to the regulatory objectives sought by this Decree in ordering their vertical separation. Likewise, when it comes to transactions among subsidiary companies, conditions of market independence or mutual independence of the parties to such transaction must be reproduced at all times.
ARTICLE 5: TRANSPARENCY AND AUDIT OF SUBSIDIARY COMPANIES. The subsidiary companies must observe high international standards of transparency, accounting, disclosure, compliance, and audit. The audit action of the Superior Court of Accounts (TSC) shall consist of carrying out compliance audits of the subsidiary companies, performed after the economic and financial activity. Operational and accounting regularity audits shall be performed by the internal audit services of the subsidiary companies, under the supervision of the Audit Committee of the Board of Directors of the National Electric Power Company Parent (ENEE) and by the annual independent external audit established in this Article. The subsidiary companies shall be subject to annual independent external audit conducted by a specialized firm of the highest standard available in the country. In the contracting of these external audits, the obligation of the auditing firm to observe the auditing standards issued by the Superior Court of Accounts (TSC) shall be included, in accordance with the provisions of Article 49 of the Organic Law of the Superior Court of Accounts, Legislative Decree No. 10-2002-E. The provisions of this article are understood without prejudice to the subsequent control and oversight that corresponds to the Superior Court of Accounts (TSC), in accordance with the Constitution of the Republic and its Organic Law.
ARTICLE 6: ASSETS, PURCHASES, AND FINANCING OF SUBSIDIARY COMPANIES. The own assets acquired by the subsidiary companies from their capital stock or their own resources shall be governed solely by this decree, the General Law of the Electrical Industry, the Commercial Code, and by the provisions of the Civil Code, under a special regime of national assets. The assets and properties owned by the National Electric Power Company (ENEE) Parent assigned to the subsidiary companies shall not form part of the assets of these and shall be governed by the legal regime applicable to the National Electric Power Company (ENEE). Increases or reductions of capital in the subsidiary companies related to movable or immovable property shall be governed by the provisions of the Commercial Code applicable to commercial companies. The National Electric Power Company (ENEE) shall establish the guidelines that will guide the regime of purchases and contracting of goods and services that each subsidiary company shall develop and implement, based on the principles of transparency, free competition, equality, and efficiency. All contracts executed by the subsidiary companies shall be governed by common law, and the State Contracting Law shall not apply to them. Each subsidiary company shall approve and execute its own regime of purchases and contracting in accordance with the principles established in this decree, including rules of publicity, competition, equality, efficiency, management of conflicts of interest, publication of awards, mechanisms for challenges, and audit. The general guidelines of the National Electric Power Company (ENEE) Parent shall not substitute the technical and economic determination of the purchasing needs of each subsidiary nor interfere in their adjudication procedures. The subsidiary companies may contract loans with the State or its autonomous institutions, as well as with international credit agencies and financial institutions, public or private, with prior authorization from the National Electric Power Company (ENEE) parent and favorable opinion of the Secretariat of State for Finance (SEFIN). They may equally issue bonds, obligations, or any other securities or debt instruments of any denomination with backing exclusively from their income or capital flows, with compliance with the opinions issued by the Secretariat of State for Finance (SEFIN) and the Central Bank of Honduras (BCH). In no case may the shares, generating plants, dams, reservoirs, networks, substations, easements, land, critical infrastructure, or other strategic assets linked to the continuity of the electrical service be committed as collateral. No debt instrument may be issued in which the control of the subsidiary companies is pledged or could be pledged.
ARTICLE 7: BUDGET AND ACCOUNTING OF SUBSIDIARY COMPANIES. A. BUDGET OF SUBSIDIARY COMPANIES. The National Electric Power Company parent shall coordinate the budgetary process of the subsidiary companies. The board of directors of each subsidiary company shall approve its draft budget in accordance with its business plan, and the Board of Directors of the National Electric Power Company (ENEE) Parent shall send to the Secretariat of State for Finance (SEFIN) a consolidated budget proposal that identifies the budgetary aggregates of expenses and investments of each company. The budgets for expenses and investments shall consist of a projection of the income statement and cash flow statement for the corresponding fiscal year, as well as a projection of the balance sheet accompanied as an annex, together with the supplementary documentation determined by the Secretariat of State for Finance (SEFIN). The National Electric Power Company parent (ENEE) must present the budget in individualized and consolidated form for all companies for the purpose of consolidation in the Non-Financial Public Sector. B. REVIEW OF SUBSIDIARY BUDGETS. The Secretariat of State for Finance (SEFIN) shall analyze the budget proposals sent by the National Electric Power Company (ENEE) and shall prepare a fiscal impact analysis evaluating whether they are consistent with fiscal goals and national planning and recommending adjustments to be made if, in its opinion, approval without modifications could cause patrimonial damage to the State or undermine the results of existing policies and plans. The review of the budgets of the subsidiary companies by the Secretariat of State for Finance (SEFIN) and the Executive Power shall fall upon the budgetary aggregates. C. INCORPORATION OF BUDGET PROPOSAL INTO GENERAL BUDGET AND REFERRAL TO NATIONAL CONGRESS. The budget proposals, accompanied by the fiscal impact analysis of the Secretariat of State for Finance (SEFIN), shall be incorporated into the draft General Budget of Income and Expenses of the Republic, with the adjustments resulting from such analysis, for presentation to the National Congress, in accordance with the budgetary formulation calendar published by the Secretariat of State for Finance (SEFIN). D. BUDGETARY MODIFICATIONS. The National Electric Power Company (ENEE) and the subsidiary companies shall direct their operations toward the achievement of the objectives reflected in their budgets. Modifications to the budgets of the subsidiary companies shall be governed by the rules established for that purpose by the Board of Directors of the National Electric Power Company (ENEE), provided that they do not affect the total budgetary ceiling allocated; otherwise, they must request an opinion from the Secretariat of Finance (SEFIN). The execution of the operational budget financed with own resources corresponds to the board of directors of each subsidiary company, without subjection to the regime of limiting credits, commitment quotas, and accrual applicable to central administration. Modifications requiring contributions from the General Budget of the Republic or that significantly affect the volume of short- and long-term debt shall require approval from the Secretariat of State for Finance (SEFIN). Operations of credit that are entered into and canceled in the same budget year shall not be considered as such. E. OPERATING DEFICIT OF ENEE DISTRIBUTION. ENEE Distribution shall include in its annual budget, in a separate and technically substantiated manner, the projected operating deficit derived from energy losses not recognized in the current tariff schedule, as well as the impact of subsidies, social tariffs, freezes, exemptions, or other applicable tariff benefits. ENEE Distribution shall be responsible for adopting the financial, commercial, operational, and administrative measures necessary to cover and progressively reduce said deficit. When the State expressly establishes subsidies, social tariffs, or other benefits that require budget compensation, these must previously have the corresponding legal authorization, source of financing, and budget allocation, in accordance with fiscal availability and the Medium-Term Fiscal Framework. F. HISTORICAL DEBT AND ACCUMULATED OBLIGATIONS. ENEE must formulate and implement its own strategy for financial restructuring and multi-year programming to address said obligations from its income, assets, recovery of losses, operational efficiencies, and other legally available sources. Only those obligations that have express sovereign guarantee and legally granted may generate responsibilities for the State, within the limits and conditions established in the respective instrument and in applicable legislation. G. RESPONSIBILITY AND FINANCIAL AUTONOMY. The National Electric Power Company (ENEE) and its subsidiary companies shall retain their operational, commercial, financial, and contractual autonomy and, consequently, shall be responsible for the obligations and commitments they undertake in the exercise of such autonomy. The execution of judgments determining responsibility shall be done under the mechanism provided and established in the Law of Economic Reactivation and Human Development contained in Legislative Decree No. 17-2026, the amendment to the Organic Budget Law, Legislative Decree No. 70-2026, and the General Provisions of the Current Budget. H. OPERATIONAL AND MARKET AUTONOMY. The foregoing provisions regulate exclusively the budgetary and fiscal treatment of contributions from the State and shall not limit the operational, commercial, financial, or contractual autonomy of the National Electric Power Company (ENEE) nor of its subsidiary companies, nor their participation in the electrical market in accordance with the current legal and regulatory framework. I. PROGRAM AGREEMENTS WITH THE STATE. In the event that the State, through the Secretariat of State for Finance (SEFIN), establishes Program Agreements with the National Electric Power Company (ENEE), which include contributions of any kind from the general budget of the State for the management of the subsidiary companies, specific objectives and goals, evaluation indicators, mechanisms for control of execution and results, and the effects derived from their non-compliance shall be defined. J. ACCOUNTING. The subsidiary companies must apply the principles established in the International Financial Reporting Standards (IFRS) applicable to Commercial Companies. To facilitate a comprehensive view of the finances of the public sector, the accounts of the subsidiary companies must be presented in accordance with the guidelines issued by the General Accounting Office of the Republic in order to allow integration in the consolidated report of the public sector.
ARTICLE 8: REGULATORY TESTING SANDBOXES. A. PURPOSE. In order to fulfill the objectives of clean energy, promote the energy transition agenda, new business models, and testing of new technologies, regulatory testing sandboxes may be established, conceived as a controlled environment to conduct tests that allow the development of pilot projects in order to facilitate research, innovation, and regulatory improvement in the field of the electrical sector. B. REGULATORY EXEMPTIONS. The provisions included in the General Law of the Electrical Industry, the regulations developed pursuant to it, and the other laws and standards that make up the legal framework of the electrical sector may be subject to regulatory exemption, in accordance with the provisions of the corresponding call for proposals. Access to the regulatory testing sandbox shall not in any case imply the granting of licenses or authorizations or the recognition of rights that could have effects outside the limits of the tests conducted within the scope of the pilot project, especially as regards their volume, duration, geographical scope, and extent. Likewise, the exemptions from the regulations provided for in this area shall not affect in any way any other activities that may be exercised by the promoter or the participants. The following may not be subject to regulatory exemption in any case: (
- i)
the rules on safety of the electrical system and emergency operation; (
- ii)
the rules on integrity of the wholesale electrical market and financial settlement; (
- iii)
the obligations of open access and non-discrimination in the use of networks; (
- iv)
the core protections for end consumers established in the General Law of the Electrical Industry; (v) the rules on prevention of corruption and promotion of free competition. C. REQUEST FOR ACCESS. Market agents may request access to their pilot projects to the regulatory testing sandbox individually or in groups, through a grouping agreement and in accordance with the provisions of the corresponding call for proposals. To be eligible, pilot projects must have technical viability, be limited, either in term, geographical scope, or volume, and propose a regulatory innovation capable of contributing to the improvement of regulation and regulatory learning, as well as generating potential benefits for consumers. To be eligible, pilot projects must additionally demonstrate: (
- i)
innovative character with respect to ordinary operation of the subsector; (
- ii)
demonstrated need for the requested regulatory exemption; (
- iii)
sufficient technical maturity for execution within the timeframe of the call for proposals; (
- iv)
measurable indicators of impact in one or more sectoral objectives (reliability, loss reduction, renewable integration, access, efficiency); and, (v) technically and financially demonstrated capacity of the promoter. D. CALLS FOR PROPOSALS. The Secretariat of State for Energy (SEN) shall approve the calls for proposals for access to the regulatory testing sandbox, with prior report from the Electrical Energy Regulatory Commission (CREE). Promoters and interested parties shall submit requests for access to the regulatory testing sandbox in the manner and timeframe established in the call for proposals. The Electrical Energy Regulatory Commission (CREE) shall evaluate the requests for access to the regulatory testing sandbox and may request a report from the System and Market Operator, depending on the regulatory exemptions involved, in order to assess the request. E. TESTING PROTOCOL. Promoters whose pilot projects have obtained a favorable preliminary evaluation shall execute a testing protocol with the Electrical Energy Regulatory Commission (CREE), which shall include the rules and specific conditions for the development of the tests of the pilot project in the regulatory testing sandbox. F. RESPONSIBILITY. Within the framework of the regulatory testing sandbox, the promoter shall act at its risk and shall be responsible for the damages that occur as a consequence of the tests due to non-compliance with its terms and conditions or due to technical or human failures during the development of the tests for which it is responsible. G. REGULATION OF REGULATORY TESTING SANDBOXES. The regulation to be issued by the Electrical Energy Regulatory Commission (CREE) shall develop the particular standards for the participation of interested parties, the agreements for the commitment of participants, and the regime of operation of the regulatory testing sandbox, including its call for proposals and approval procedures, monitoring mechanisms, early termination, cessation, penalties, responsibilities, guarantees, and evaluation of results. In the terms and conditions for conducting the tests, established in the manner stipulated by the regulation, it may not in any case be provided that the State must compensate the promoter for the patrimonial losses resulting from its participation in the regulatory testing sandbox. H. RESULT OF THE TEST. Upon conclusion of the testing period, the CREE shall issue a public evaluation report that shall recommend one of the following actions: (
- i)
termination of the pilot project; (
- ii)
extension for an additional and defined period to complement evidence; (
- iii)
formal initiative for regulatory reform to incorporate the innovation into the general applicable framework. The decision for extension must be justified against criteria predefined in the testing protocol.
- i)
- i)
ARTICLE 9: POWERS OF INTERVENTION IN THE NATIONAL PROGRAM FOR LOSS REDUCTION. The National Electric Power Company (ENEE) is hereby instructed to, under the directives and coordination of the Executive Power, intervene in, evaluate, adopt the necessary measures, and set a deadline for completion of the National Program for Loss Reduction authorized by Legislative Decree No. 46-2022, based on the provisions of the General Law of Public Administration. The report resulting from the evaluation shall be published and made available to the public through the official communication channels of the National Electric Power Company (ENEE).
ARTICLE 10: SUCCESSION OF ODS BY OPERATION OF LAW AND TRANSFER OF ASSETS AND PERSONNEL TO OSM. A. TRANSITION OF SYSTEM OPERATION. The Electrical Energy Regulatory Commission (CREE) is hereby instructed to continue supervising the process of dissolution and liquidation of the National Electrical System Operator Association (ODS) in accordance with its bylaws, as well as the implementation of the System and Market Operator (OSM), ensuring the integration of its organization, putting it into operation, and entry into service in accordance with the provisions of this decree. Until entry into operation of the System and Market Operator (OSM), the National Electrical System Operator Association (ODS) shall continue temporarily exercising the functions of system operation and market administration, under the supervision of the Electrical Energy Regulatory Commission (CREE), guaranteeing at all times the continuity, security, and quality of the electrical service; B. TRANSFER AND SUCCESSION. To ensure operational continuity, the transfer of assets and liabilities resulting from the liquidation to the System and Market Operator (OSM) is hereby ordered in accordance with the Bylaws of the National Electrical System Operator Association, as well as the transfer of the personnel of the National Electrical System Operator Association (AOSEN), respecting their labor rights. As of the date of entry into operation of the OSM, it shall succeed by operation of law to the ODS Operator in all assets, rights, information, records, databases, systems, equipment, computer programs, licenses, permits, authorizations, contracts, agreements, files, accounts, funds, receivables, and other assets necessary for the exercise of the functions of operation of the National Electrical System and administration of the electrical market. The transfer shall operate as a matter of right, without need for assignment, novation, additional authorization, or consent of third parties, without prejudice to the notifications and registry registrations necessary for their enforceability. Public institutions, registries, banks, contractors, agents of the electrical market, and other related entities must recognize the System and Market Operator (OSM) as the legal successor to the ODS with respect to the assets, rights, contracts, information, registries, systems, obligations, and legal relationships transferred. The System and Market Operator (OSM) shall assume the obligations, liabilities, and contingencies directly linked to the assets, contracts, legal relationships, and functions transferred, in accordance with the inventory and transfer balance approved by the Electrical Energy Regulatory Commission (CREE). Liabilities not directly linked to the operation of the national electrical system and the administration of the electrical market, as well as contingent, contentious, or undetermined liabilities as of the date of transfer, shall continue to be subject to the ODS liquidation process, without prejudice to the reserves, guarantees, or coverage mechanisms authorized by the CREE to protect the rights of creditors, workers, and other legitimately interested third parties. C. TRANSFER AND CONTINUITY OF PERSONNEL. ODS personnel shall be transferred to OSM under the figure of employer substitution provided for in Article 28 of the Labor Code, when applicable, without interruption of continuity and with recognition of seniority, salary, category, acquired rights, labor benefits, social security, and other applicable labor conditions. The liquidating commission must prepare, update, and submit for approval of the Electrical Energy Regulatory Commission (CREE) the inventory of assets, rights, obligations, contracts, personnel, files, systems, accounts, funds, receivables, and contingencies subject to transfer or liquidation. Said inventory shall serve as the basis for the delivery and receipt minutes between the ODS, through its liquidating commission, and the System and Market Operator (OSM). D. PUTTING THE OSM INTO OPERATION. The Electrical Energy Regulatory Commission (CREE) shall approve the effective date of entry into operation of the System and Market Operator (OSM) and the corresponding transfer, upon verification of the minimum technical, administrative, financial, computer science, and operational conditions necessary to assume its functions without interruption. The resolution of the Electrical Energy Regulatory Commission (CREE) shall have enabling effects for the transfer of assets, rights, contracts, information, personnel, and other elements necessary for operation. The first Board of Directors of the System and Market Operator (OSM) must be designated and in function within a maximum period of sixty (60) business days counted from the entry into force of this decree. The System and Market Operator must begin operations within a maximum period of one hundred forty (140) business days from the entry into force of this Decree. Once in function, the Board of Directors of the System and Market Operator (OSM) shall have fifty (50) business days to issue its internal regulation containing the operational and administrative provisions necessary for the organization and functioning of the System and Market Operator (OSM).
ARTICLE 11: STEERING COMMITTEE AND TECHNICAL UNIT FOR IMPLEMENTATION AND MONITORING OF THE ELECTRICAL SUBSECTOR REFORM. A. STEERING COMMITTEE. The Steering Committee for the Reform of the Electrical Subsector is hereby created, as a temporary instance of superior coordination, strategic monitoring, and resolution of inter-institutional matters linked to the implementation of this Law. The Committee shall be coordinated by the Secretariat of State for the Office of the Presidency and shall have as its object ensuring the ordered, timely, and coherent execution of the implementation roadmap of the reform. The Committee shall be composed of the institutions determined by the regulation, and must include, at a minimum, the Secretariat of State for the Office of the Presidency, the Secretariat of State for Energy (SEN), the Secretariat of State for Finance (SEFIN), the National Electric Power Company (ENEE), and the Electrical Energy Regulatory Commission (CREE). This committee must, within one hundred twenty (120) days following the entry into force of this decree, prepare the bylaws and regulations governing the governance in each of the subsidiary companies created and send them to ENEE Parent for approval in its capacity as sole shareholder, those who compose it, and other aspects for their functioning; B. TECHNICAL UNIT. The Technical Unit for Implementation and Monitoring of the Electrical Subsector Reform is hereby created, attached to the Secretariat of State for the Office of the Presidency, as a temporary instance of technical support, operational coordination, monitoring, early warning, and preparation of inputs for decision-making by the competent bodies; The Technical Unit shall not substitute the legal, regulatory, budgetary, administrative, or operational competencies of the institutions responsible for implementing the contents of this decree, nor shall it affect the functional and decision-making independence that corresponds to the Electrical Energy Regulatory Commission (CREE). C. IMPLEMENTATION ROADMAP. The Technical Unit shall prepare and maintain updated a comprehensive implementation roadmap of the reform, with identification of milestones, institutional responsible parties, deadlines, risks, mitigation measures, fiscal impact when applicable, progress status, and pending decisions. The roadmap shall be approved by the Steering Committee and shall serve as an instrument for monitoring the execution of this Law; D. MONITORING OF CRITICAL MILESTONES. The Technical Unit shall monitor, in particular, the milestones linked to the transformation and division of the National Electric Power Company (ENEE), the putting into operation of the OSM, and the other measures necessary for the implementation of this decree; E. LIAISON AND INFORMATION. The institutions linked with the implementation of this Law must designate institutional liaisons with sufficient capacity to coordinate internally the provision of information, validate schedules, and channel the decisions that correspond to their competent authorities. Said institutions must provide the Technical Unit with the information necessary for the fulfillment of its mandate, without prejudice to the applicable rules on confidentiality, secrecy, and protection of personal data; F. REPORTS, ALERTS, AND ESCALATION. The Technical Unit may issue reports, recommendations, early warnings, progress dashboards, and proposals for corrective measures, which shall constitute technical inputs for decision-making by the competent bodies; When it identifies delays, critical risks, non-compliance with milestones, or inter-institutional conflicts that may affect the implementation of the reform, the Technical Unit shall escalate them to the Steering Committee for consideration and possible adoption of the measures that correspond within the scope of competence of each institution. G. PUBLICITY AND CONFIDENTIALITY. The Technical Unit shall prepare internal monitoring reports with the periodicity established by the regulation and shall publish quarterly progress reports on the official websites of the Secretariat of State for the Office of the Presidency and the Secretariat of State for Energy (SEN), without prejudice to the information that must remain confidential in accordance with the Law; H. FINANCING AND REGULATION. The expenses necessary for the operation of the Steering Committee and the Technical Unit shall be financed from the budget of the Secretariat of State for the Office of the Presidency, without prejudice to the technical or financial cooperation that may be managed in accordance with the Law; The Regulation for the operation of the Steering Committee and the Technical Unit must be issued by the Executive Power through the Secretariat of State for the Office of the Presidency, within a period not exceeding forty-five (45) business days counted from the entry into force of this decree, and must develop the organization, composition, technical profiles, conflict of interest regime, duties of confidentiality, coordination mechanisms, monitoring procedures, resources, internal deadlines, form of closure, and other aspects necessary for the operation of the Steering Committee and the Technical Unit; I. EXTINCTION. The Steering Committee and the Technical Unit shall become extinct as a matter of right once the comprehensive implementation roadmap approved in accordance with this article is completed, without prejudice to the ordinary mechanisms of monitoring, control, oversight, and accountability that correspond to the competent institutions.
ARTICLE 12: RESPECT FOR THE RIGHT OF UNIONIZATION AND COLLECTIVE BARGAINING, PRESERVATION OF ACQUIRED RIGHTS DERIVED FROM COLLECTIVE EMPLOYMENT CONTRACTS.
Related laws
- Reglamento — Reglamento Centro de Conciliación y Arbitraje del Colegio de Abogados de Honduras (CECA-CAH)
- Regulations on Conciliation and Arbitration of the Inter-American Chamber of Commerce — This law establishes the Conciliation and Arbitration Center of the Civil Engineers Association of Honduras (CCA-CICH) to resolve construction conflicts and other disputes through conciliation and arbitration, offering individuals and companies a faster alternative to courts. The Center appoints trained arbitrators and mediators, establishes clear procedures, and maintains confidentiality of proceedings.
- Reglamento — Reglamento del Centro de Conciliación y Arbitraje del Colegio de Ingenieros Civiles de Honduras (CCA-CICH)
- Decreto Legislativo No. 46-2022 — Ley Especial para Garantizar el Servicio de la Energía Eléctrica como un Bien Público de Seguridad Nacional y un Derecho Humano de Naturaleza Económica y Social — This law declares electricity as a public good and human right, and orders the rescue of the state company ENEE by renegotiating energy contracts, canceling the private operator ODS, eliminating tax subsidies to generators, and building renewable plants. It benefits poor consumers with free electricity and reduces costs through audits and public control of the national electrical system. (Decree 46-2022, 2022)
- Decreto Legislativo No. 24-2008 — Ley de Protección al Consumidor — This law protects consumers' rights in Honduras by regulating relationships between sellers and buyers of goods and services. It establishes basic rights such as truthful information, safe products, warranties, and access to justice, prohibiting abusive practices like hoarding, false advertising, and unjustified charges. It creates the General Directorate for Consumer Protection to enforce the law and authorizes consumer associations to defend their interests. (Decree 24-2008)